Current Projects
Construction and Design
The Reno-Tahoe Airport Authority (RTAA) is committed to enhancing its airports, Reno-Tahoe International and Reno-Stead, through initiatives like the MoreRNO Infrastructure Program.
This page provides an overview of all current construction and design projects under RTAA, including those within and beyond the MoreRNO program
Guideline Documents
Current Projects
Terminal Loop Road
Updated: October 10, 2024
Project Description: | Design & Reconstruction of PCC portion of Terminal Loop Road, ADA, and Pedestrian/Terminal Safety Improvements |
Current Phase: | Design |
Design Services Awarded: | 10/14/2021 |
Design Cost: | $1,176,000 |
Design Consultant: | Kimley-Horn |
Sealed Proposals Opened: | 09/02/2021 |
Construction Cost: | $12,200,000 |
Contractor: | Q&D |
Anticipated Completion Date: | COMPLETED |
AUTO EXIT LANES
Project Description: | Install one directional exits from the concourses to the terminal to eliminate the need to staff the exit. |
Current Phase: | Completed |
Design Services Awarded: | 09-6-2022 |
Design Cost: | $45,500 |
Design Consultant: | Paul Cavin Architect |
Sealed Proposals Opened: | 08-10-2023 |
Construction Cost: | $410,000 |
Contractor: | Q&D |
Anticipated Completion Date: | COMPLETED |
AIRFIELD SIGNAGE RENAMING
Project description: | Updating the taxiway nomenclature to current FAA standards to help reduce confusion and incursions. |
Current phase: | Construction |
Design services awarded: | 04-13-2023 |
Design cost: | $248,000 |
Design consultant: | Wood Rodgers |
Sealed proposals opened: | 3-21-2024 |
Construction cost: | $3,780,000 |
Contractor: | Royal Electric |
Anticipated completion date: | August 2025 |
VALE PCAIRE & GPU REPLACEMENT
Updated: September 9, 2024
Project Description: | Replace 23 pre-conditioned air units and ground power units to reduce emissions by the airport |
Current Phase: | Construction |
Design Services Awarded: | 01/25/22 |
Design Cost: | $120,000 |
Design Consultant: | PK Electrical |
Sealed Proposals Opened: | 04/17/2023 |
Construction Cost: | $6,903,768.00 |
Contractor: | Q&D Construction |
Anticipated Completion Date: | 02/28/2025 |
TWY B/M RECONSTRUCTION & GA RUNUP AREAS PROJECT (RNO)
Project Description: | Reconstruct segment of TWY B on either side of 7-25, Reconstruct TWY M, construct two new GA runup area along TWY C |
Current Phase: | Design |
Design Services Awarded: | June 2021 |
Design Cost: | $430,732 |
Design Consultant: | Wood Rodgers |
Sealed Proposals Opened: | 05/14/2021 |
Construction Cost: | $8,767,767 |
Contractor: | Granite Construction |
Anticipated Completion Date: | 10/01/2024 |
TICKETING HALL EXPANSION CMAR (RNO)
Project Description: | Expansion of Ticketing Hall Area via Construction Manager at Risk |
Current Phase: | CMAR-Design |
Design Services Awarded: | July 2021 |
Design Cost: | $2,202,821 |
Design Consultant: | RS&H |
CMAR Preconstruction Services Awarded: | 10/14/2021 |
CMAR Preconstruction Cost: | $300,000 |
CMAR: | McCarthy Building Companies |
Sealed Proposals Opened: | 08/16/2021 |
CMAR Construction Cost: | TBD |
Construction Cost: | TBD |
Contractor: | McCarthy Construction |
Anticipated Completion Date: | COMPLETED |
Please send your Engineering and Design questions to engineeringhelp@renoairport.com