RNO Master Plan: Project 2

Project 2:  Airfield Runway Incursion Mitigation Improvements
(south end of Taxiway Alpha)

Project Description

At the far south end of Taxiway Alpha, the FAA has identified a Runway Incursion site, requiring mitigation for safety purposes. This small airfield project has been included in much larger airfield reconstruction project also known as the Runway 16R/34L Reconstruction project. The Runway Incursion Mitigation (RIM) work involves the rounding off of a squared-off portion of pavement. Because this RIM work is included in Phase 2 of a larger airfield project, all schedule and cost information below represents the larger project – Runway 16R/34L Reconstruction, Phase 2.

Current Phase

Design for Phase 2 is in progress. Funding for construction is not yet available.

(Click image for larger version.)

Primary Contact: Tony Curatolo, Senior Engineering Project Manager

Delivery Method: Design-Bid-Build

Project Completion Date (Anticipated): February 2022

Total Project Cost (Estimate): TBD

Funding Sources: FAA Airport Improvement Program Grant Funding (93.75%)
Passenger Facility Charge Funding (6.25%)

CONTRACTS Design Construction Project Management /
Construction Management
Contract Administrative
Services
Vendor Wood Rodgers TBD Atkins Wood Rodgers
Award June 2018 February 2020 February 2020 February 2020
Completion February 2020 November 2021 February 2022 February 2022
Cost (estimate) $2,500,000 TBD TBD TBD

 

Customer Feedback