Reno-Tahoe International Airport Thu, September 2nd - 7:33 am
The Airport Authority  »   Airport Construction & Development

Airport Construction & Development

American Recovery & Reinvestment Act of 2009 (ARRA)
The American Recovery and Reinvestment Act of 2009 (ARRA) was signed into law by President Obama on February 17, 2009.  Included in this unprecedented multi-billion dollar effort to help save and create jobs was a direct infrastructure investment in airport facilities of $1.1 billion that was awarded by the Federal Aviation Administration (FAA) to airports through Airport Improvement Program (AIP) grants.  Airport projects which improve capacity, safety, security and aircraft noise compatibility are all eligible with priority given to ready-to-go projects that could be completed within two years.

The following two projects are being funded with ARRA grants.

arra_photo_200

Terminal Apron Rehabilitation - Phase 12 Construction
Project Description:
Reconstruction of approximately 13,800 square yards of Portland Cement Concrete (PCC) and 1,600 square yards of Asphalt Concrete Pavement (ACP) apron adjacent to the terminal concourses.
Sealed Proposals Opened:April 30, 2009
Project Cost:$2,400,460 (100 percent ARRA funded)
Contractor:
Granite Construction Company
Scheduled Completion Date:
August 12, 2010
  
Terminal Apron Rehabilitation - Phase 13 Construction
Project Description:
Reconstruction of approximately 16,000 square yards of Portland Cement Concrete (PCC) and 800 square yards of Asphalt Concrete Pavement (ACP) apron adjacent to the terminal concourses.
Sealed Proposals
Opened:
August 27, 2009
Project Cost:
$2,662,819 (100 percent ARRA funded)
Contractor:
Q&D Construction
Scheduled Completion
Date:

August 12, 2010


ARRA Certification and Progress
The Governor, mayor or other chief executive, as appropriate, is required to certify that the infrastructure investment has received the full review and vetting required by law and that the chief executive accepts responsibility that the infrastructure investment is an appropriate use of taxpayer dollars.

Krys T. Bart, A.A.E., President/CEO of the Reno-Tahoe Airport Authority, certified on Tuesday, May 12, 2009 that the above ARRA infrastructure projects have received the review and vetting required by law and are an appropriate usage of taxpayer funds. 

Section 1511 Certification
ARRA fund tracking is available at www.recovery.gov

Terminal Apron Rehabilitation - Phase 14 Construction
Project Description:
Reconstruction of approximately 16,300 square yards of Portland Cement Concrete (PCC) and 400 square yards of Asphalt Concrete Pavement (ACP) apron adjacent to terminal concourses. 
Sealed Proposals Opened:
March 4, 2010
Project Cost:
$3,124,124
Contractor:
Granite Construction Company
Scheduled Completion Date:
TBD
  
Airfield Lighting Systems Improvements
Project Description:Project consists of the airfield lighting vault reconstruction and the installation of runway guard lights, taxiway lights and control upgrades.
Sealed Proposals Opened:
August 27, 2009
Airfield Lighting Vault Project Cost:
$717,769
Airfield Lighting Vault Contractor:
Q&D Construction, Inc.
Airfield Lighting Vault Scheduled Completion Date:
June 15, 2010
  
Airfield Lighting Modifications Project Cost:
$2,935,043
Airfield Lighting Modifications Contractor:
Vellutini Corporation (dba Royal Electric)
Airfield Lighting Modifications Scheduled Completion Date:
February 5, 2011


new_tower_10.06.09_031_large_768
New Air Traffic Control Tower Facilities
The existing 70-foot tall Air Traffic Control Tower (ATCT) was constructed in 1954 and served the airport’s needs for more than 50 years, but it does not comply with the new more stringent seismic structural standards and is therefore being replaced. A new 200-foot tall tower with an 11,000 square foot base building began construction in January 2008 on property leased by the Reno-Tahoe Airport Authority to the Federal Aviation Administration (FAA).  The new facility is scheduled to be operational in late 2010. The new tower will include the most technologically advanced equipment available and will have unobstructed views of all aircraft movement areas as well as the surrounding airspace.